2018-19 EXAMINATIONS
PART II (Second Year, Final Year)
MSCI 231 Introduction to Operations Management
CLOSED BOOK EXAMINATION
2 HOURS
This paper consists of three questions. All questions carry equal marks. Answer any two of these for full marks. If you attempt an answer to all three only two will be marked.
You may use a calculator and a standard dictionary. There is a formula sheet at the end of this paper.
Complete the details required on the front sheet of your answer booklet now. Do not turn over this page until told to do so.
Question 1
An operator of a tram service in a large city is concerned about the capacity and punctuality of its service on a particular line where it crosses several busy main roads. It is concerned about over-crowding on its trams and the problem that, at certain times, passengers are being stopped from boarding over-crowded trams, and are complaining to local politicians.
On one route, trams call every 6 minutes at a stop outside a main station and then travel to the city centre. The following table shows, for one hour during the peak period, the number of passengers arriving at the stop in the interval between successive trams. It also shows the capacity of the trams arriving at this stop. They arrive empty from the main depot and there are three sizes of tram.
Exhibit 1: Passenger arrivals and tram capacity
Time |
18:06 |
18:12 |
18:18 |
18:24 |
18:30 |
18:36 |
18:42 |
18:48 |
18:54 |
19:00 |
Passengers arriving |
250 |
243 |
239 |
157 |
176 |
160 |
199 |
182 |
154 |
184 |
Tram capacity |
150 |
150 |
150 |
250 |
250 |
250 |
250 |
200 |
200 |
200 |
a) Assuming that no passengers were left waiting by the tram that preceded the first (at 18:06), how many passengers will be prevented from boarding the tram at 18:30, and what is the largest number of passengers prevented from boarding during the hour? (20% of the mark)
b) What is the maximum time any passenger will have to wait due to overcrowding during this hour? You can assume (i) there is no particular discipline in the crowd of waiting passengers that means the first to arrive will be the first to board but (ii) anyone prevented from boarding a tram is always preferred for the next tram. (20% of the mark)
c) If you cannot assume anyone prevented from boarding a tram is always preferred for the next tram, what is the maximum time any passenger will have to wait due to overcrowding? (20% of the mark)
In practice the larger tram units, with a capacity of 250 passengers, were often delayed in coming from the depot to the first point at which they picked up passengers. In a sample of 80 trams over the period of a week it was found that the maximum time of arrival ahead of the schedule was 4 minutes and the maximum lateness behind schedule was 12 minutes. On average, trams were 1.5 minutes late. The standard deviation over lateness was 2.8 minutes.
d) What is the maximum lateness that the company can set and publish as a standard if it is to achieve an upper process capability index of 2.0, and what is the status of its process if it sets the standard at the maximum lateness it measured? (20% of the mark)
e) Discuss briefly how well the standard definition of quality as ‘Consistent conformance to customer expectations’ could apply in the context of a tram operator. (20% of the mark)
Question 2
The operator of a tram service in a large city runs a maintenance depot where it has to store spare tram wheels in order to replace worn or broken wheels on its trams. Wheels are ordered in batches of 40 from the supplier on the first day of every calendar month. The operations director is concerned about the high level of stock in the depot, and the length of time some wheels are remaining in stock and becoming corroded. It costs about £10 per wheel to hold stock for one year. But the operations
director is also concerned about the cost of administration at the depot, including the time that staff spend on placing orders. For example, it costs about £50 to place every order, whether this is for a single, small item or a large batch of large items.
a) If the tram operator is using all the wheels it orders in a year, what is the optimal size of each order and how many times per annum are orders being unnecessarily placed? (20% of the mark)
b) Assuming a constant rate of usage of the wheels over the year, by how much does the current annual cost based on monthly orders exceed the optimal annual cost? (20% of the mark)
c) Which of the five principal reasons for holding inventory are relevant to the depot’s stocks of
wheels, and in what way does this suggest that using Economic Order Quantity calculations might be
a mistake? (20% of the mark)
d) Concern with excess inventory has led the operations director of the tram operating company to take a renewed interest in the Toyota Production System – and considering whether it could be relevant to tram operations generally, not just the maintenance depot. Outline the elements of the Toyota Production System. (20% of the mark)
e) Give an example of how the ‘line-stop’ authority principle might be applied in a mass
transportation service such as a tram operator, and identify the risk of applying the principle in this case. (20% of the mark)
Question 3
The operator of a tram service in a large city is concerned about the derailment risk at one particular point in the tram network. It has decided to undertake a project to revise the track layout and the table below shows the main activities that will be needed. It also indicates the pre-requisite activities, and estimates of activity duration in terms of most likely, best and worst times, in weeks.
Exhibit 2: Track layout revision activities
Activity |
|
Pre-requisite activities |
Minimum duration |
Most likely duration |
Maximum duration |
A |
Remove old track |
|
1 |
2 |
2 |
B |
Repair damaged surface |
A |
2 |
2 |
2 |
C |
Clear kerbs etc |
|
1 |
1 |
3 |
D |
Remove pavement |
C |
1 |
3 |
4 |
E |
Lay new pavement |
D |
3 |
5 |
7 |
F |
Prepare track bed |
B, D |
4 |
5 |
9 |
G |
Lay new track |
F |
4 |
7 |
8 |
H |
Static testing |
G |
1 |
1 |
2 |
I |
Traffic testing |
G |
2 |
4 |
5 |
a) Find the critical path and the minimum project duration based on the means of the duration estimates. (20% of the mark)
b) During the project, the company carrying it out was required to report progress as an earned value analysis at the end of each week. If the project were given a budget of £1.6 M, and at week 5 it reported that about 15% of the work had been completed, and that it had spent £0.38M, what were the schedule and cost variances at this point? Use your value for the mean project duration rounded to the nearest whole week. (20% of the mark)
c) In lectures we looked at the critique of managing projects by techniques like Earned Value
Analysis in an interview with the CEO of a firm that developed new sonar equipment. What was the critique, and is it as relevant to a project changing a track layout as it is to a project developing new sonar products? (20% of the mark)
Shortly after carrying out this work the tram operator became aware of the Croydon incident:
‘Seven people were killed and a further 51 injured when [a] tram derailed in Croydon, south London, as it entered a sharp bend at almost four times the speed limit. Analysis of the on-board data recorder shows the regular service brake was not applied until around 2.5 seconds before the tram reached a 20km/h (13mph) speed limit sign at the Sandilands curve where the accident occurred at 6.07am on November 9 last year. Its speed decreased from 49mph to 46mph by the time it passed the sign. The hazard brake was not used’ (The Telegraph, 20 February 2017).
The company commissioned a risk assessment, and the diagram below shows the event tree for safeguards and recovery actions if a derailment happened, following the normal conventions of annotating branches with probabilities. It has assumed that the probability of a derailment is 1 in 200 per year. The UK regulator has a standard risk acceptance criterion which states that the probability of accidents killing 50 or more should be less than 1 in 5000 per year.
Exhibit 4: Event tree for safeguards and recovery actions applying after a derailment
Initiating event Stabilising system Impact protection Driver speed control Evacuation procedure Fatalities
0.7 0
0.3 0.9 0
0.1 0.9 0
0.1 0.6 10
0.4 50
d) Find the probabilities of scenarios in which there are fatalities, and determine whether risk in this system is acceptable. (20% of the mark)
e) It is sometimes said that the effective management of risk requires ‘A joint feeling of doubt and hope’ (Vogus et al, 2014). Briefly explain why. (20% of the mark)
版权所有:编程辅导网 2021 All Rights Reserved 联系方式:QQ:99515681 微信:codinghelp 电子信箱:99515681@qq.com
免责声明:本站部分内容从网络整理而来,只供参考!如有版权问题可联系本站删除。